Auburn Way South (SR 164) Corridor Improvements – Muckleshoot Plaza to Dogwood St SE

Client: City of Auburn

Role: Project Manager & Design Manager | CH2M

Dates: September 2013 to December 2016

Stephanie managed the project as well as the project design (including preliminary design alternatives) for the City of Auburn. This project included access management, U-turns, transit stops, and street lighting. It also widened Auburn Way South (SR 164) to accommodate turn lanes and pedestrians. Sidewalks and pedestrian push buttons were upgraded to meet current ADA standards including countdown pedestrian signals and audible pedestrian push buttons. Traffic signals were also upgraded to improve both phasing and signal head visibility. Stephanie also led all of the WSDOT coordination including Channelization Plans for Approval and Design Variance Documentation.